Report insights / Ports and alternative fuels

Alternative-fuel ships are on orderAre ports ready?

Ships need more than the ability to use a new fuel: they need ports that can deliver it consistently. Three cases show how alternative fuels connect with everyday operations.

Share this article

Contents

Four points to take away

  • Choose the fuel and the bunkering route.Assess ship capability, routes and supply arrangements together.
  • Define what readiness covers.Read the evidence by fuel and operating method.
  • Infrastructure also needs suitable supply.Check quantities, quality and emissions evidence.
  • Ship–shore operations must fit the schedule.Bunkering windows, SIMOPS and contingencies all affect operations.
01

Ships are on order. Where will they bunker?

A dual-fuel ship’s ability to use a new fuel does not guarantee that the fuel will be available on its existing routes. The technical choices made when ordering a ship ultimately depend on networks for production, transport, storage and bunkering.

LR’s Fuel for Thought: Ports reports an alternative-fuel-capable orderbook of 1,942 ships in January 2026, including 385 methanol-capable and 45 ammonia-capable ships. At the same point, 222 ports offered LNG bunkering and 25 actively offered methanol bunkering. These figures show that ships and supply networks are developing at different speeds for different fuels.

Alternative-fuel-capable orderbook

Two selected fuels | Unit: ships

Methanol
385
Ammonia
45
0200400 ships
January 2026; LR analysis of Clarksons data. The selected categories do not represent the entire orderbook.

Ports offering bunkering

Two selected fuels | Unit: ports

LNG
222
Methanol
25
0125250 ports
January 2026; Clarksons figures cited on report p. 8. Planned ports are excluded.

For shipowners and technical teams, the practical questions matter more than global totals: which ports will the ship call at, how much fuel will it need, when will it need it, and can supply be sustained? Some gas carriers can use their own cargo as fuel, so not every alternative-fuel-capable order represents demand for port bunkering.

02

What does each fuel require from a port?

A single “ready” label cannot describe a port’s preparedness. The same port may routinely supply LNG, still be developing its methanol market, and have completed only a risk assessment for ammonia.

Biofuel blends

Stage described in the report

Often able to use existing oil storage, transport and bunkering equipment

What to check

Consistent quality, storage conditions, blend ratios, feedstocks and sustainability certification

Existing supply chains are an advantage, but compatibility between ship systems and fuel specifications still needs confirmation.

LNG / bio-LNG / e-methane

Stage described in the report

LNG already has a relatively mature bunkering network

What to check

Cryogenic storage, boil-off gas management, supply arrangements and methane emissions

Bio-LNG and e-methane can use similar infrastructure; their emissions benefits still depend on production pathways and methane leakage or slip.

Methanol / ethanol

Stage described in the report

Methanol is commercially supplied at some hubs; ethanol has fewer examples

What to check

Toxicity, flammability, material compatibility and sources of low-emission fuel

Being liquid at ambient temperature allows some chemical infrastructure to be used, but cargo-handling capability must still be developed into a bunkering service.

Ammonia

Stage described in the report

Commercial deliveries have emerged; many other ports remain at the trial or preparation stage

What to check

Toxicity control, leak dispersion, emergency response, personnel competence and fuel supply

Each berth and operating scenario needs its own assessment; LNG experience cannot simply be transferred.

Hydrogen

Stage described in the report

Mainly short-distance, harbour-service and demonstration applications

What to check

Storage volume, cryogenic or high-pressure conditions, leakage and ignition risks

A hydrogen import terminal does not, by itself, mean that a port can bunker hydrogen-fuelled ships.

Based on report pp. 10–17 and 35. This is a snapshot at the time of the research, not a live list of port supply services.

03

“Ready” needs a defined scope

When reading port announcements, ask what the milestone demonstrates: completed research, established procedures, one successful operation, or the ability to accept recurring orders? Each type of evidence answers a different question.

PRL stands for Port Readiness Level. It uses levels 1–9 to describe a port’s progress towards bunkering a particular marine fuel, across three phases: research, development and deployment.

PRL 1–3

Research

Understand the need: assess the fuel’s relevance to the port, stakeholder interest and the information still missing.

PRL 4–6

Development

Turn plans into trials: decide the direction, establish an assessment-based operating framework and conduct pilot testing.

PRL 7–9

Deployment

Move into operations: start with individual projects, scale up and progress towards routine service. Reaching level 7 does not mean fuel is already available on demand.

The full tool, Port Readiness Level for Marine Fuels (PRL-MF), was developed by WPCAP and IAPH as a self-assessment framework applied fuel by fuel. Its use also requires a clear statement of storage and bunkering methods, scope, assessment date and outstanding work.

PRL provides a common language; it does not replace authority approvals, individual operational assessments or suppliers’ delivery commitments. The colour-coded overview on report p. 34 is the report’s own classification, not a set of official PRL scores for the ports. This article therefore focuses on specific events and their scope rather than turning different achievements into a single ranking.

04

Three ports, three kinds of progress

A delivery, a trial and a licensing system answer different questions. Ulsan, Rotterdam and Singapore help illustrate the conclusions that each kind of progress can support.

Ulsan

23 April 2026

Ammonia delivery

What does a 600-tonne delivery prove?

The report records Lotte Fine Chemical supplying around 600 tonnes of green ammonia to Antwerpen by port-to-ship (PTS) bunkering in Ulsan for sea trials before delivery. The Ulsan maritime authority confirmed the bunkering and safety-management preparations, describing it as a world-first commercial milestone of its kind.

This demonstrates one completed delivery under specific vessel and operational arrangements. It does not establish that any customer can obtain the same service at any time.

Official announcement ↗

Rotterdam

April 2025

Ammonia transfer trial

From trials to project-based readiness

Following an ammonia ship-to-ship transfer trial, the port announced that it had completed PRL 6 and moved to PRL 7, with safety procedures supporting bunkering on a project basis. The trial used grey ammonia to validate the operating arrangements.

Procedures and operating experience are meaningful progress. Sources of low-emission fuel, routine availability and customer service remain separate conditions to verify.

Official announcement ↗

Singapore

From Jan 2026

Methanol suppliers

A licensing framework for methanol supply

MPA announced licences for three methanol suppliers, covering 1 January 2026 to 31 December 2030. Selection considered supply-chain reliability, operational readiness, safety systems and fuel sustainability certification.

The framework provides a basis for supply and oversight. Each order still requires confirmation of quantity, quality, bunkering time, berth and contract terms.

Official announcement ↗

These cases involve different fuels and operating conditions. They are not a ranking of overall port capability.

05

From infrastructure to suitable fuel

The physical ability to store and transfer fuel addresses only part of the supply question. Shipowners also need to know whether production has started, whether volumes are available for delivery, and whether quality and emissions evidence meet the intended use.

Grey, blue and green ammonia, for example, share the same principal chemical constituent when bunkered, but differ in production pathways and upstream emissions. Methanol raises a similar issue: being able to bunker conventional methanol does not ensure a continuous supply of suitable bio-methanol or e-methanol. Fuel names and colour labels cannot replace specific production, traceability and emissions data.

Announced capacity is not available supply

Report p. 13 cites June 2026 data showing announced renewable and low-carbon methanol project capacity of 61.8 Mt/year, while renewable methanol capacity expected to be operational by the end of 2031 is estimated at 6–12 Mt/year.

The first figure includes low-carbon methanol; the second covers only renewable methanol. Their scopes differ. These are project-capacity figures and expectations, not actual marine-fuel deliveries, and cannot be used directly to calculate a project completion rate. Mt means million tonnes.

The final delivery leg also needs bunker vessels, berth time, permits and emergency-response arrangements. These capabilities must be maintained even when initial demand is low, potentially increasing delivery costs per unit. Completed port infrastructure does not remove the effects of price, supply frequency and demand commitments on utilisation.

Cost assessments should therefore consider the fuel quotation alongside storage and transport, bunkering services, waiting time, deviations and contingency arrangements. Green shipping corridors can coordinate supply and demand along a route, but joining an agreement does not mean that every service is already available. Voyage requirements, actual contracts and delivery evidence still matter.

06

Bunkering safety, schedules and cargo operations

Even when onboard systems and shore equipment each meet their respective requirements, their ability to work together at a particular berth and under defined operating conditions still needs confirmation. This interface is central to alternative-fuel bunkering.

Ship-to-ship (STS), truck-to-ship (TTS) and port-to-ship via shore piping (PTS) each have different supply capabilities and operational limits. Fuel type, ship–shore layout, transfer conditions, neighbouring activities and weather can all affect the bunkering arrangements available.

Practical questions for ship–shore readiness
AreaQuestions to resolveEvidence to retain
Equipment and transferAre connections, hoses, pressure, temperature and flow rates compatible?Interface data and operating conditions confirmed by both parties
Communication and shutdownWho gives the instruction and who stops pumping in an abnormal situation? How is emergency shutdown (ESD) coordinated?Communication procedures, assigned responsibilities and applicable test records
Areas and peopleWho could be affected by a leak? How will isolation, evacuation and rescue be arranged?Berth risk assessment, emergency plans and drill records
Cargo and schedulesCan cargo operations continue during bunkering? When must other activities stop?SIMOPS assessment, operating windows and restrictions

SIMOPS (simultaneous operations) allows bunkering and cargo work to overlap, potentially reducing additional time in port. It also increases interactions between activities. Exclusion zones may overlap with lifting, lashing or personnel routes, so a successful arrangement at another port cannot simply be applied to this ship.

07

Turning fuel choices into a workable voyage plan

A usable fuel plan should connect ship and voyage requirements with evidence for supply, operations and contingencies. The following process offers a sequence for discussion among shipowners, technical teams, procurement and operations.

From requirements to contingencies

5 steps
  1. Define requirements

    List planned routes, fuel needs and bunkering windows; identify range and storage limits.

    Check supply against needs
  2. Confirm the fuel

    Obtain deliverable volumes, quality specifications, origin documents and delivery conditions.

    Match supply to the port
  3. Confirm the port

    Confirm the specific berth, bunkering method, supplier qualifications and applicable permits.

    Check site conditions
  4. Confirm operations

    Confirm ship–shore interfaces, SIMOPS, weather limits and emergency arrangements.

    Plan for the remaining risks
  5. Prepare contingencies

    Plan alternative bunkering locations or confirmed feasible fuel arrangements, assess additional time and cost, and agree responsibilities.

An operational-readiness process adapted from report pp. 55–60. This is an editorial synthesis, not a statutory approval procedure. If a critical condition is unmet, return to the relevant step and resolve it.

Digital tools can make these arrangements easier to coordinate. Mass flow meters (MFM) support quantity measurement, electronic bunker delivery notes (e-BDN) retain transaction records, and shared schedule information helps coordinate bunker vessels and service windows. Fuel quality, sustainable origin and emissions intensity still require supporting documents and verification; an electronic delivery note cannot establish all of them.

08

My reading notes: clarify delivery conditions

My central question when reading this report is: after a port completes a bunkering operation, what else must be in place before a shipowner can include it in a regular service?

Bringing this question into newbuilding, procurement and operational discussions helps align design conditions with actual use. Equipment, permits, supply and personnel readiness have different owners. Defining deliverable quantities, bunkering windows, restrictions and responsibilities early provides a basis for later adjustments.

Port readiness changes. Plans should keep supply arrangements, operating limits and contingencies up to date, while accounting for time and cost, so that each port call rests on traceable information.

Reay Huang Maritime Notes

Frequently asked questions

Does one completed bunkering operation establish routine supply?

One operation can demonstrate delivery capability under specific conditions. Routine supply also needs reliable fuel sources, service windows, people and equipment, permits and continuing commercial arrangements.

If biofuels can use existing equipment, can a ship simply switch fuels?

Fuel specifications, blend ratios, storage stability, system compatibility and applicable requirements still need checking. Bio-based origin and recognition of emissions reductions also require their own evidence.

Does a port’s absence from the report mean it has no capability?

No. The report covers selected ports and publicly reported milestones. Omission or a lack of information does not establish a lack of capability. Taiwanese ports were not systematically assessed either; local authority and supplier information needs to be checked separately.

Can shore-side bunkering arrangements be assessed using only the IGF Code?

The IGF Code primarily addresses ships and their fuel systems. Shore-side and in-port operations also involve local authority, port and supplier requirements. Both sides of the ship–shore interface, and their interaction, need to be checked.

Sources and scope

  1. LR | Fuel for Thought: Ports. Released 2 November 2026; principal references: pp. 6–18, 22, 26–27, 35–38, 43, 47 and 49–60. The report states a data cut-off of 28 September 2026; individual statistics have their own dates.
  2. PRL-MF | Official tool description. Purpose of the self-assessment tool, its nine levels, and the research, development and deployment phases.
  3. Ulsan Regional Office of Oceans and Fisheries | Ammonia bunkering announcement. 23 April 2026; quantity, method and safety-management preparations.
  4. Port of Rotterdam | Ammonia bunkering pilot. 14 April 2025; grey ammonia used in the trial and the project-based scope of PRL 7.
  5. MPA | Methanol bunker supplier licences. 24 November 2025; suppliers, licence period and assessment criteria.

Information reviewed as of 2 November 2026. This article describes events and readiness reported in public sources, not live port inventories or service guarantees. Differences exist between the report’s port overview and some appendix descriptions. This article uses specific cases and traceable official statements rather than adopting that overview as a port ranking.

The interpretations, process and practical questions in this article are the author’s synthesis for readers. They do not constitute approval of any ship, terminal or operation, nor do they represent the employer’s official position. Actual operations must follow applicable rules, permits and project assessments.